The Building (Approvals and Practitioners) Act 2026 passed the NSW Parliament on 4 August 2026 and received assent on 14 August 2026.
Only two limited provisions commenced on assent. Most of the Act will commence on a date or dates appointed by proclamation, following development of the supporting regulation.
When the relevant provisions commence, the Act will consolidate significant parts of NSW’s building approval, certification and practitioner-registration framework. It provides for the repeal of:
- the Building and Development Certifiers Act 2018,
- the Building and Development Certifiers Regulation 2020,
- the Design and Building Practitioners Act 2020,
- the Design and Building Practitioners Regulation 2021,
- the Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021.
Some key changes and inclusions:
Defective building work limit
A civil action for loss or damage arising out of or in connection with defective building work may not be brought more than 10 years after the date of completion of the work. This provision does not extend a shorter limitation period that may otherwise apply and does not limit claims relating to death or personal injury.
Duty of care
The Act substantially re-enacts the statutory duty of care currently contained in the Design and Building Practitioners Act 2020. A person who carries out construction work has a duty to exercise reasonable care to avoid economic loss caused by defects for current and subsequent owners. A person who owes a duty of care under this part cannot delegate the duty.
Staged approval
Staged approvals will be permitted. A separate application may be made for each stage of the building work, and the approval authority must consider the effect of the other stages when deciding each application.
Prefabricated buildings
The Act formally brings prefabricated and modular buildings into the building-approval framework. It introduces requirements for manufacturers, including prefabricated building declarations, installation instructions and information that must accompany the supply of a prefabricated building.
Fire safety certificates
Under the new completion-approval framework, where a fire safety certificate is required, it will be issued by the approval authority rather than the building owner.
Some new and changed terminology:
- Approval authority – now includes certifiers (appropriately registered persons) along with the local council, or the Planning.
- Building approvals – Formerly construction certificates, authorises building work to be carried out.
- Completion approvals – Formerly occupation certificates, when building work or a change of building use has been completed.
- Building work– physical activity involved in the erection of a building and includes work prescribed by the regulations.
- Construction work – work that includes constructing, altering, adding to, repairing, renovating or protectively treating a building; preparing relevant design work; manufacturing or supplying building products used in that work; and supervising, coordinating, project-managing or otherwise having substantive control over the work.
- Prefabricated building– a substantially complete building or room that is manufactured away from the building site. It also includes a modular building component that will become an installed building element that cannot be inspected without destructive testing or opening.
The passage of the Act is only the first step. The supporting regulations are currently still under development with consultation continuing into 2027. We will monitor the reforms and provide further updates on what they mean in practice – particularly for fire safety related compliance, engineering and expert witness matters.